Project: Pottsville Street Stormwater Improvements
Location: Pottsville Street, Herndon Borough, Northumberland County, PA
Solicited by: Tonia Troup, Project Coordinator, SEDA-COG
📍 201 Furnace Road, Lewisburg, PA 17837
📞 (570) 524-4491
🌐 www.seda-cog.org
📅 Publication Date: June 27, 2025
🕙 Submission Deadline: July 22, 2025, by 10:00 AM (prevailing time)
Submission Instructions
-
Submit three (3) sealed hard copies
-
Clearly mark envelope:
"Engineering Services Quotation – Pottsville Street" -
Deliver to:
Tonia Troup, Project Coordinator
SEDA-COG, 201 Furnace Road, Lewisburg, PA 17837 -
No faxed or emailed submissions accepted
Project Overview
-
Funded by a Community Development Block Grant (CDBG)
-
Purpose: Mitigate stormwater issues on Pottsville Street and restore roadway
-
Scope includes:
-
2 new box inlets
-
18" corrugated plastic piping
-
4" rolled curb on both sides
-
Milling and resurfacing with base and wearing courses
-
Re-grading for proper drainage
-
Engineer Responsibilities
-
Full design and documentation
-
All necessary permits (excluding surveys/environmental/historic reviews)
-
Bidding coordination and contract administration
-
Pre- and post-construction meetings
-
Site visits and final inspection
-
“As Built” drawings (1 hard copy + 1 digital)
-
Adherence to PA Prevailing Wage Rates
Required Meetings
-
Kick-off
-
Two development meetings
-
Final design approval/ad readiness
-
Preconstruction coordination
-
Optional pre-bid meeting
-
Bid opening and award recommendation
-
Preconstruction conference
Indicate any additional meetings and associated costs on the estimate form.
Bidding & Contract Coordination
-
Prepare and distribute bid documents (up to 10 sets)
-
Manage ad placements (ad costs reimbursed by Borough)
-
Provide bid tabulation, award recommendation, contract execution support
-
Issue:
-
Notice of Intent to Award
-
Notice to Proceed
-
Final completion documents
-
Construction Supervision
-
Minimum 2 site visits + final inspection
-
Monitor conformance, review submittals, disapprove non-compliant work
-
Review and approve payment requests
-
Serve as Borough’s site representative
-
Frequency of visits must be estimated in quotation based on projected timeline
(Costs will not be adjusted if duration changes)
Deliverables
-
Project design and construction documents
-
Cost estimates at preliminary and final stages
-
Project design timeline with milestones
-
List of subconsultants (if applicable)
-
Final “As Built” drawings (physical + digital)
Terms of Payment
-
Lump sum contract (includes all services and reimbursables)
-
Monthly billing based on percentage completed
-
Payment contingent on DCED disbursement
Compliance Requirements
MBE/WBE Participation Goals
-
MBE: 5%
-
WBE: 3%
(for projects with CDBG/ESG/HOME funds)
Section 3 Participation (24 CFR Part 75)
-
Applies only to construction contracts over $200,000
-
Engineer should support client’s compliance with:
-
25% of labor hours = Section 3 workers
-
5% of labor hours = Targeted Section 3 workers
-
Professional services labor hours may count but must be reported separately
-
Evaluation Criteria
Quotations will be scored on:
-
Responsiveness to RFQ
-
Relevant experience and past performance
-
Quality of previous work
-
Resources and track record of timely completion
-
Cost
-
Commitment to MBE/WBE participation
Required Documentation
-
Completed Standard Engineering Estimate
-
Minimum of two (2) references (similar projects, last 3 years)
-
MBE/WBE Certification (if applicable)
-
Solicitation & Commitment Statement
-
Professional Liability Insurance coverage limits
Contact for Questions
Tonia Troup
📧 ttroup@seda-cog.org
📞 (570) 524-4491